Timeline

Mid-2007
  • Advocated
    • Community Trails Alliance advocates for a Whitewater River bike path
Z
late-2009

Studied

  • Late Corridor Study completed
mid-2010
  • Updated
  • Update to Coachella Valley Non-motorized Transportation Plan completed. 
late-2011
  • Vehicles
  • CV Link, then Parkway 1e11, proposed to include Low Speed Electric Vehicles (LSEVs)
Early-2012

Reporting

  • Preliminary Study Report (PSR); Air Quality Benefits Estimate Report, Economic Benefits Report Completed
l
Early-2013

Begin Plan

  • Begin CV Link Master Plan
Mid-2013

Design

  • Complete concept design elements
j
Mid-2014

Electric Vehicle Plan

  • Complete Coachella Valley Neighborhood Electric Vehicle Plan
Z
Early-2015
  • Finished Plan
  • Complete Master Plan
Mid-2016
  • First Phase Design
  • Complete detailed design of first phase
2017

Construction Starts

  • Begin Construction
2018

Grand Opening of 1st Segment

  • Ramon Road to Vista Chino
2020

Construction

  • Additional 20 miles under construction
2021

Promontory Point

  • March 2021 – Groundbreaking of La Quinta & Indio Bridge

Palm Desert

  • October 2021 – Completion of 3.5 mile on-street segment 
2022

Demuth Park

  • March 2022 – Palm Springs Groundbreaking at Demuth Park